Deliverables | Completion Date |
1. The Contractor shall submit a revised, final work plan electronically | No later than 30 days after Contract execution |
2. The Contractor shall submit the final project budget template electronically | No later than 30 days after Contract execution |
3. The Contractor shall submit a progress report electronically | No later than March 8, 2024 |
4. The Contractor shall attend an individual grantee check-in with OPHP | No later than March 22, 2024 |
5. The Contractor shall submit a final report electronically | No later than June 15, 2024 |